A Cultural Resources Survey of 72.4 Miles (1,755 Acres) within the Tonto National Forest for the Salt River Project Coronado to Silverking 500-kV Transmission Line in Gila and Pinal Counties, Arizona (2017)
DOCUMENT Full-Text Reese Cook. David Bustoz. Erik Steinbach.

SRP requested that Logan Simpson conduct an intensive cultural resources survey of a 72.4-mile-long and 200-ft-wide (1,755-acre) segment of the SRP Coronado to Silverking 500-kV transmission line within the TNF and private land. This survey was requested for general inventory purposes and also in advance of proposed vegetation-maintenance activities within the project corridor. In addition, SRP may conduct maintenance or construction projects within the limits of the project corridor. Vegetation...