A Historic Properties Treatment Plan for Four Prehistoric Sites Along the Salt River Project's Proposed Southeast Power Link 230kV Transmission Line Corridor, Maricopa County, Arizona (2022)
DOCUMENT Full-Text Sebastian Chamorro. Angela Huster.

Salt River Project (SRP) is proposing to construct a new 230kV transmission line in Maricopa County, Arizona (Project). The proposed Project entails the construction of seven miles of new overhead power lines that will follow a previously approved route. The proposed overhead transmission line will require the placement of 56 tubular steel pole structures. The corridor for the proposed Project varies between 100–205 feet (ft) wide. Additionally, a new 230/69kV receiving station will be built in...