A Class Ill Cultural Resources Inventory of 275 Miles of the Western Transmission System, from the Navajo Generating Station in Page, Coconino County, Arizona, to the McCullough Substation near Henderson, Clark County, Nevada - Volume 3: Nevada (2017)
DOCUMENT Full-Text David L. Lewandowski.

The Salt River Project Agricultural Improvement and Power District (SRP) requested that Logan Simpson conduct a Class Ill cultural resources inventory of 7,200 acres (275 miles) of the existing Western Transmission System (WTS) right-of- way (ROW) in Arizona, Utah, and Nevada. The project area is a linear easement for the existing extra-high voltage 500-kV transmission line, the WTS. The transmission line is part of the Navajo Generating Station (NGS) transmission system and extends from the NGS...