Rio Verde Canal (Site Name Keyword)

1-1 (1 Record)

Salt River Project Pinnacle Peak to Papago Buttes Project, Assessment of Cultural Resources (1985)
DOCUMENT Full-Text Richard W. Effland.

Salt River Project (SRP) proposes to construct a 230 kV transmission line to connect the Pinnacle Peak, Brandow, and Papago Buttes substations. Archaeological Consulting Services (ACS) was contracted to perform an assessment of impacts to cultural resources that would be caused by the project. ACS is responsible for assessing potential impacts to historical and archaeological sites as well as architectural resources in the vicinity of the new right-of -way. One hundred percent survey of the...