Old State Route 80 (Site Name Keyword)
1-1 (1 Record)
Treatment and Data Recovery Plan for the SRP Palo Verde to Pinal West 500 kV Transmission Line, Maricopa and Pinal Counties, Arizona (2007)
DOCUMENT
Full-Text
Salt River Project Agricultural Improvement and Power District (SRP) plans to construct a new 500 kV transmission line between the existing Hassayampa Switchyard, west of Phoenix, Maricopa County, Arizona, and the proposed Pinal West Substation, western Pinal County, Arizona (Figure 1). Designated the Palo Verde to Pinal West (PV-PW) transmission line, this powerline is the first of two that SRP plans to eventually construct between the Hassayampa Switchyard and...