AZ U:6:265 (ASM) (Site Name Keyword)
1-1 (1 Record)
A Cultural Resource Survey Report and Archaeological Monitoring and Discovery Plan for the Salt River Project 69-kV Transmission Line Pole Replacement Between Rio Verde and Fountain Hills, Maricopa County, Arizona (2005)
DOCUMENT
Full-Text
Salt River Project (SRP) maintains a 69-kilovolt (kV) transmission line between the Glenbrook substation in Fountain Hills and the Rio Verde substation in the community of Rio Verde in Maricopa County, Arizona (Figure 1). The transmission line is currently supported by 30-year-old wooden poles, which generally follow the alignment of McDowell Mountain Road. In order to improve the overall safety and durability of the transmission line, SRP intends to replace all of...