AZ 11:11:192 (ASM) (Site Name Keyword)
1-1 (1 Record)
A Cultural Resources Survey of 22.1 Acres of State and Private Lands West of the Tonto National Forest Boundary for the SRP Silver King to Goldfield 230kV Upgrade, Queen Valley, Pinal County, Arizona (2008)
DOCUMENT
Full-Text
The Salt River Project (SRP) is planning to upgrade the current carrying capacity of 18.3 miles of the existing Silver King to Goldfield 230kV line north of Queen Valley and Superior, Pinal County, Arizona. In order to accomplish this, SRP plans to “bundle” the existing 230kV conductors by adding a second conductor to each of the three existing single-conductor phases. This 230kV line was originally intended for two circuits of bundled conductors and permitted for such on Forest Service lands by...