An Archaeological Evaluation of a Proposed Electric Power Line Construction Project on Tonto Creek near El Oso Road and Highway 188, Gila County, Arizona (1983)
DOCUMENT Full-Text Lyle M. Stone.

On December 12, 1983, Lyle M. Stone and Douglas R. Mitchell of Archaeological Research Services, Inc. performed an archaeological survey along the route of a proposed power line construction project on Tonto Creek near the intersection of El Oso Road and Highway 188, Gila County, Arizona. This project, proposed by Salt River Project, will entail: (1) the construction of 755 ft of new underground electric line; (2) the construction of 1200 ft of new overhead line; and (3) the modification of...


An Archaeological Survey of a 2.3 Mile Long Right-of-Way for a Proposed 22 kV Distribution Line on the Tonto National Forest, Tonto Basin District, Gila County, Arizona (1982)
DOCUMENT Full-Text Lyle M. Stone.

On July 28, 1982, Lyle M. Stone of Archaeological Research Services, Inc. performed an archaeological survey of a 2.3 mile by 100 ft wide right-of-way for a proposed 22 kV distribution line on the Tonto National Forest near Punkin Center, Gila Country, Arizona. The proposed Salt River Project distribution line will serve an AT&T relay station in the vicinity of Four Peaks. This survey was requested by Salt River Project in order to determine if important cultural resources (prehistoric or...


Historic Cultural Resources in Relation to the Central Arizona Water Control Study (1983)
DOCUMENT Full-Text Lyle M. Stone. James E. Ayres.

Flooding along the Salt, Gila, Verde, and Agua Fria Rivers in February and March of 1978 resulted in extensive damage to property in Central Arizona and in the disruption of ground transportation and commerce in the greater Phoenix area. Major flooding also occurred along these rivers in December, 1978 and February, 1980. The recognition of this flooding problem, and of requirements for the regulatory storage of Central Arizona Project (CAP) water, prompted the U.S. Department of the Interior,...


The Roosevelt Community Development Study, Number 13, Volume 2: Meddler Point, Pyramid Point, and Griffin Wash Sites (1994)
DOCUMENT Full-Text Mark D. Elson. Deborah L. Swartz. Douglas B. Craig. Jeffrey J. Clark.

The Roosevelt Community Development Study (RCD) was one of three data recovery mitigative studies that the Bureau of Reclamation funded to investigate the prehistory of the Tonto Basin in the vicinity of Theodore Roosevelt Dam. The series of investigations constituted Reclamation's program for complying with historic preservation legislation as it applied to the raising and modification of Theodore Roosevelt Dam. Reclamation contracted with Desert Archaeology, Inc. to complete the research for...