The Museum of Northern Arizona investigated four sites along the Silver King to Kyrene, East End, Transmission System. NA15,693 is the remains of a portion of the Magma Arizona Railroad Company narrow gauge line and associated features. The line was used between 1915 and 1923 to haul freight, passengers, and mail between Superior and Webster (Magma Junction). NA15,718 includes the remains of several Salado field houses and associated agricultural features. The site occupants practiced a mixed...
Archaeological Investigations: Salt River Project Silverking-Kyrene Transmission Line, Tonto National Forest, Pinal County, Arizona: A Research Plan for Three Sites Along the Silverking-to-Kyrene, East End, Transmission Line, Tonto National Forest, Pinal County, Arizona (1978)
The research plan outlines a framework for investigating 3 archaeological sites along the Silverking-to-Kyrene, East End, Transmission Line, a part of the Coronado Project. The 3 sites, initially recorded during a recent survey by the Museum of Northern Arizona, are a large lithic scatter associated with linear rock alignments, a possible 1-room structure associated with linear rock alignments, and an abandoned railroad grade. The plan discusses specific means by which the scientific potential...
A Class III Cultural Resources Survey of the Salt River Project 230-kV and 500-kV Transmission Line Rights-of-Way from Silver King to the Western Forest Boundary, Tonto National Forest, Mesa and Globe Districts, and Private Lands near Superior, Pinal County, Arizona (2020)
SRP contracted SWCA Environmental Consultants (SWCA) to conduct a Class III cultural resources survey along a 15.1-mile-long stretch of the Goldfield-Silver King 230-kilovolt (kV) and Browning to Silver King 500-kV electrical transmission line right-of-way (ROW) in Pinal County, Arizona. The purpose of the survey was to identify cultural resources that are listed in or eligible for listing in the National Register of Historic Places (NRHP) so that SRP can take the necessary measures to avoid or...
A Cultural Resources Survey of 84.3 Acres of Tonto National Forest and Private Lands for the SRP Silver King to Goldfield 230kV Upgrade, North of Superior, Pinal County, Arizona (2008)
SRP is planning to upgrade the current carrying capacity of 18.3 miles of the existing Silver King to Goldfield 230kV line. In order to accomplish this, SRP plans to “bundle” the existing 230kV conductors by adding a second conductor to each of the three existing single-conductor phases. To add the new conductors, SRP will need to re-open some original access roads, and the selected wire, puller, sleeving, and anchor sites used during the original 1978 line construction. The existing...