An Archaeological Survey of the Orme Reservoir (1975)
DOCUMENT Full-Text Veletta Canouts.

This report is a statement concerning the assessed impact of the proposed Orme Reservoir on the archaeological resources. The Orme Reservoir is one phase of the Bureau of Reclamation's Central Arizona Project plan to impound and distribute water from the Colorado River to central and southern Arizona. To be located at the confluence of the Salt and Verde rivers, the Orme Reservoir will flood approximately 24,000 acres of bottomland along both rivers. Previous archaeological data from the area...


An Evaluation of Historic Cultural Resources in Relation to the Central Arizona Water Control Study (1984)
DOCUMENT Full-Text Lyle M. Stone. James E. Ayres.

This is a final, summary report on historic cultural resources in relation to the Central Arizona Water Control Study (CAWCS). The objectives of the CAWCS were to identify and evaluate alternative measures for flood control and regulatory water storage in Central Arizona in conjunction with construction of the Central Arizona Project. Having considered numerous alternative plans to meet these objectives, the Bureau of Reclamation defined a preferred alternative (Plan...


Historic Cultural Resources in Relation to the Central Arizona Water Control Study (1983)
DOCUMENT Full-Text Lyle M. Stone. James E. Ayres.

Flooding along the Salt, Gila, Verde, and Agua Fria Rivers in February and March of 1978 resulted in extensive damage to property in Central Arizona and in the disruption of ground transportation and commerce in the greater Phoenix area. Major flooding also occurred along these rivers in December, 1978 and February, 1980. The recognition of this flooding problem, and of requirements for the regulatory storage of Central Arizona Project (CAP) water, prompted the U.S. Department of the Interior,...


SRP 69 kV Subtransmission Line Reconductoring Project, Draft Environmental Assessment (2002)
DOCUMENT Full-Text Environmental Services Group, ENTRANCO, Inc..

This Environmental Assessment (EA) has been prepared to evaluate Salt River Project (SRP) proposed plans to perform major maintenance to two 69 kilovolt (kV) subtransmission lines within an SRP power line utility corridor easement. Although this project is not a Federal undertaking or action, this EA has been prepared in accordance with the guidelines contained in the Bureau of Indian Affairs (BIA) Manual Release No. 9303, NEPA Handbook, September 24, 1993. The manual provides guidance for...