Archaeological Monitoring of Construction Activities along El Paso Natural Gas Company Pipeline Rights-of-Way across the Gila River below Gillespie Dam, Maricopa County, Arizona (1992)
DOCUMENT Full-Text Robert B. Neily.

Archaeological Consulting Services, Ltd. (ACS) monitored the realignment of the 1100 and 1103 pipelines across the Gila River below Gillespie Dam. The work was performed to determine if any buried archaeological deposits or features were present within the boundaries of previously recorded sites and to mitigate the effects of the project on such features. The work was conducted at the request of El Paso Natural Gas Company (EPNG) and based on recommendations resulting from the initial survey of...


An Archaeological Survey of Two Arizona River Crossings Along the All-American Pipeline (1984)
DOCUMENT Full-Text Margerie Green.

Archaeological Consulting Services (ACS) conducted an archaeological survey of two major Arizona river crossings along the proposed route of the All-American Pipeline at the request of Dr. Ed Weil, Cultural Resources Manager, Applied Conservation Technology (ACT). ACT is coordinating the entire cultural resource effort along this proposed pipeline from the Gulf of Mexico to the Pacific Ocean and has subcontracted with ACS to undertake the Arizona portion of the route. Because the placement of...


An Archaeological Survey of Two Staging Areas and a Portion of Two Parallel El Paso Natural Gas Company Pipelines Near Gillespie Dam on the Gila River, Maricopa County, Arizona (1991)
DOCUMENT Full-Text Robert B. Neily.

Archaeological Consulting Services, Ltd. (ACS) conducted a cultural resource survey of two segments of El Paso Natural Gas Company (EPNG) pipelines to be rerouted across the Gila River below Gillespie Dam. For reasons of safety, EPNG intends to bury the two lines that currently cross the river as bridges. In addition, two proposed staging areas for storage of pipe and equipment during the construction of the rerouted pipelines were also surveyed. The project was conducted at the request of Dr....


Archaeology at the Gillespie Dam Site: Data Recovery Investigations for the Palo Verde to Pinal West 500 kV Transmission Line, Maricopa County, Arizona (2011)
DOCUMENT Full-Text Uploaded by: Alaina Harmon

In this report, the results of data recovery efforts conducted for the Palo Verde to Pinal West transmission line project at the Gillespie Dam site, AZ T:13:18 (ASM), in the Gila Bend area of the Gila River are presented. The site is a prehistoric Hohokam-Patayan settlement with an overlay of Historic era material. Fieldwork primarily occurred within the construction staging area of a transmission tower. Although covering less than an acre, the staging area contained surprising numbers of...


Cultural Resources Survey for the SRP Palo Verde to Pinal West 500 kV Transmission Lines, Maricopa and Pinal Counties, Arizona (2007)
DOCUMENT Full-Text Tiffany C. Clark. T. Kathleen Henderson.

This report presents the results of Class III cultural resources surveys conducted for the Palo Verde to Pinal West Transmission Line Project. The work was sponsored by Salt River Project (SRP) in support of two proposed 500 kV transmission lines that will connect the existing Hassayampa Switchyard, west of Phoenix, Maricopa County, Arizona, and the proposed Pinal West Substation, western Pinal County, Arizona. The cultural resources studies described here include three previous archaeological...


A Cultural Resources Survey of the Proposed Hassayampa-Jojoba Transmission Line, Maricopa County, Arizona (2002)
DOCUMENT Full-Text Regina L. Chapin-Pyritz. Matthew Hill, Jr..

GBPP (Gila Bend Power Partners) proposes to construct and operate a 500kV transmission line, which will deliver electrical power from the Hassayampa Switchyard south of Wintersburg, Arizona to the Jojoba Switchyard currently under construction in south-central Maricopa County, Arizona. The project will increase the transmission of electrical power into areas surrounding metropolitan Phoenix, and will promote economic development of benefit to the people of Arizona. GBPP retained EPG...


The El Paso Natural Gas Line No. 2000 Conversion Project: An Archaeological Re-Survey of the Former All American Pipeline Across La Paz, Yuma, Maricopa, Pinal, Pima, and Cochise Counties, Arizona (2000)
DOCUMENT Full-Text Chris D. North.

In April and May 2000, SWCA, Inc., Environmental Consultants (SWCA) conducted cultural resource surveys for EPNG's Line No. 2000 Project, surveying the former All American Pipeline in Cochise, La Paz, Maricopa, Pima, and Pinal counties for the Arizona segment. At the request of EPNG, SWCA began the cultural resources survey for this project in April 2000 in support of an Environmental Assessment (EA) being prepared by ENSR, Inc., in conjunction with a pipeline acquisition, conversion, operation...


Letter to Dr. James George, El Paso Natural Gas Company regarding Monitoring of Emergency Salvage and Construction Activities at the Pipeline near Gillespie Dam (1993)
DOCUMENT Full-Text Barbara Macnider.

People were sent out to the pipeline near Gillespie Dam to monitor emergency salvage and construction activities in the vicinity of site AZ T:13:18 (ASM). The site is a Classic Period Hohokam village that also has both prehistoric and historic canal alignments. In all instances, the pipeline crews respected the sensitivity of the cultural resources and restricted their work to the existing El Paso Natural Gas Company (EPNG) right-of-way.


Trails, Rock Features, and Homesteading in the Gila Bend Area: A Report on the State Route 85, Gila Bend to Buckeye Archaeological Project (2008)
DOCUMENT Full-Text Uploaded by: adam brin

The Arizona Department of Transportation plans to widen State Route 85 to a four-lane freeway in the area between Buckeye and Gila Bend. This report presents the results of archaeological data recovery investigations conducted along State Route (SR) 85 for the Arizona Department of Transportation (Contract No. 02-59) by a research team assembled by the Office of Cultural Resource Management, Department of Anthropology at Arizona State University. The Area of Potential Effect (APE) was located...


Treatment and Data Recovery Plan for the SRP Palo Verde to Pinal West 500 kV Transmission Line, Maricopa and Pinal Counties, Arizona (2007)
DOCUMENT Full-Text T. Kathleen Henderson.

Salt River Project Agricultural  Improvement and  Power District  (SRP)  plans  to construct a new  500  kV  transmission  line  between  the  existing  Hassayampa  Switchyard,  west  of Phoenix, Maricopa County, Arizona, and the proposed Pinal West Substation, western Pinal County, Arizona (Figure 1). Designated the Palo Verde to Pinal West (PV-PW) transmission line,  this  powerline  is  the  first  of two  that SRP  plans  to  eventually  construct between  the Hassayampa  Switchyard  and...