The following report presents the results of a 16-mile survey of the Verde Circuit 12kV distribution lines between Stewart Mountain and Granite Reef Dams, conducted by Statistical Research, Inc. (SRI), for the Salt River Project (SRP). Following the collection of permits and a systematic check of all records pertaining to archaeological resources in the proposed area of study, field investigation of the distribution lines was conducted from October 8 to 11, 1997. Field investigation of the...
An Archaeological Survey of the Salt River Project Verde Circuit 12kV Distribution Line from Saguaro Lake to Granite Reef Dam, Maricopa County, Arizona, Draft Report (1998)
The following report presents the results of a 16-mile survey of the Verde Circuit 12kV distribution lines between Stewart Mountain and Granite Reef Dams, conducted by Statistical Research, Inc. (SRI), for the Salt River Project (SRP). Following the collection of permits and a systematic check of all records pertaining to archaeological resources in the proposed area of study, field investigation of the distribution lines was conducted from October 8 to 11, 1997. Field investigation of the...
A Class I Inventory of 9.61 Miles for the Thunderstone to Verde 69 kV Rebuild, Maricopa County, Arizona (2001)
On December 15, 2000, Entranco was authorized by Salt River Project (SRP) to conduct a Class I Inventory of an approximately 9.61-mile-long, variable width corridor from the Thunderstone Receiving Station to the Verde Substation in Maricopa County, Arizona. The project area includes Bureau of Indian Affairs right-of-way across the Salt River Pima-Maricopa Indian Community, and land under the jurisdiction of the Bureau of Reclamation, operated and managed by the Central Arizona Project and...
SRP 69 kV Subtransmission Line Reconductoring Project, Final Environmental Assessment (2002)
This Environmental Assessment (EA) has been prepared at the request of the Salt River Pima Maricopa Indian Community (SRPMIC) to evaluate Salt River Project (SRP) proposed plans to perform major maintenance to two 69 kilovolt (kV) subtransmission lines within an SRP power line utility corridor easement. Although this project is not a Federal undertaking or action, this EA has been prepared in accordance with the guidelines contained in the Bureau of Indian Affairs (BIA) Manual Release No. 9303,...