AZ U:9:62 (ASU) (Site Name Keyword)
1-5 (5 Records)
Arizona Public Service Company (APS) proposes to rebuild an existing 230 kV transmission line which connects the Pinnacle Peak and Ocotillo substations. The portion of the line which currently lies within the Salt River channel north of Mesa and south of the Salt River Pima-Maricopa Indian Community (SRPMIC) needs to be relocated due to the extensive damage caused by severe flooding over the past ten years. APS proposes to move the right-of-way out of the channel and onto the north terrace...
The Beeline Archaeological Project (1990)
The Salt River Project (SRP) and Arizona Public Service Company (APS) constructed three transmission lines along a portion of the Beeline Highway on the Salt River Pima-Maricopa Indian Community (SRPMIC). SRP proposed to build a new line that connects the Pinnacle Peak, Brandow, and Papago Buttes substations. At the same time, APS proposed to realign two existing transmission lines and move them out of the Salt River channel and onto the north terrace above the river. Prior to construction,...
A Cultural Inventory of the Salt River Indian Reservation, Arizona (1972)
This document consists of site descriptions for sites located on the Salt River Indian Reservation Lands. Those contributing content to the report include Gerald Bair, Susan B. Belt, Dav Buge, Thomas Cartledge, William G. Holiday, Susanne LaFollette, Minnabell E. Laughlin, Chad Phinney, Erwin R. Ray, Linda Richards, Helen P. Wells, Regge N. Wiseman, Robert York, and Betsy R. Zeligs.
Research Design for Data Recovery for the Salt River Project and Arizona Public Service Transmission Line Facilities Along the Beeline Highway (1985)
Salt River Project (SRP) and Arizona Public Service Company (APS) propose to construct three transmission lines along a portion of the Beeline Highway on the Salt River Pima-Maricopa Indian Community (SRPMIC). SRP proposes to build a new line which will connect the Pinnacle Peak, Brandow, and Papago Butte substations. APS proposes to realign two existing transmission lines and move them out of the Salt River channel and onto the north terrace above the river. Archaeological Consulting Services...
Salt River Project Pinnacle Peak to Papago Buttes Project, Assessment of Cultural Resources (1985)
Salt River Project (SRP) proposes to construct a 230 kV transmission line to connect the Pinnacle Peak, Brandow, and Papago Buttes substations. Archaeological Consulting Services (ACS) was contracted to perform an assessment of impacts to cultural resources that would be caused by the project. ACS is responsible for assessing potential impacts to historical and archaeological sites as well as architectural resources in the vicinity of the new right-of -way. One hundred percent survey of the...