Draft: Treatment and Work Plan for Archaeological Investigations and Monitoring at Eight Sites Along the Southwest Valley 500 kV Transmission Line Project, Maricopa County, Arizona

Summary

APS and SRP were issued a Certificate of Environmental Compatibility (CEC) by the Arizona Corporation Commission for their Southwest Valley 500kV Transmission Line Project (Southwest Valley Project). The project consists of approximately 37 miles of 500 kilovolt (kV) transmission line to interconnect electric generation resources in the west valley with the existing 230kV system in the metropolitan Phoenix area.

Cite this Record

Draft: Treatment and Work Plan for Archaeological Investigations and Monitoring at Eight Sites Along the Southwest Valley 500 kV Transmission Line Project, Maricopa County, Arizona. Kris Dobschuetz, Matthew E. Hill, Jr., Sharon K. Bauer. 2002 ( tDAR id: 413589) ; doi:10.6067/XCV8413589

This Resource is Part of the Following Collections

Spatial Coverage

min long: -112.747; min lat: 33.218 ; max long: -112.276; max lat: 33.518 ;

Record Identifiers

EPG Cultural Resource Services Research Paper No.(s): 1

File Information

  Name Size Creation Date Date Uploaded Access
2002_DobscheutzHillBauer_DraftTreatment_OCR_PDFA.pdf 54.13mb Jun 1, 2002 Aug 25, 2016 10:13:10 AM Confidential
This file is unredacted.

Accessing Restricted Files

At least one of the files for this resource is restricted from public view. For more information regarding access to these files, please reference the contact information below